35 Guarantees, commitments and risks

Guarantees

 

December 31, 2012

December 31, 2013

(€ million)

Unsecured guarantees

Other guarantees

Total

Unsecured guarantees

Other guarantees

Total

Consolidated subsidiaries

 

11,350

11,350

 

11,961

11,961

Unconsolidated subsidiaries

 

161

161

 

160

160

Joint ventures and associates

6,208

892

7,100

6,274

223

6,497

Others

2

289

291

2

174

176

 

6,210

12,692

18,902

6,276

12,518

18,794

Other guarantees issued on behalf of consolidated subsidiaries of €11,961 million (€11,350 million at December 31, 2012) primarily consisted of: (i) guarantees given to third parties relating to bid bonds and performance bonds for €7,858 million (€7,511 million at December 31, 2012), of which €4,920 million related to the Engineering & Construction segment (€5,491 million at December 31, 2012); (ii) VAT recoverable from tax Authorities for €1,408 million (€1,370 million at December 31, 2012); and (iii) insurance risk for €293 million reinsured by Eni (€298 million at December 31, 2012). At December 31, 2013, the underlying commitment covered by such guarantees was €11,781 million (€11,266 million at December 31, 2012).

Other guarantees issued on behalf of unconsolidated subsidiaries of €160 million (€161 million at December 31, 2012) consisted of letters of patronage and other guarantees issued to commissioning entities relating to bid bonds and performance bonds for €147 million (€154 million at December 31, 2012). At December 31, 2013, the underlying commitment covered by such guarantees was €29 million (€34 million at December 31, 2012).

Unsecured guarantees and other guarantees issued on behalf of joint ventures and associates of €6,497 million (€7,100 million at December 31, 2012) primarily consisted of: (i) an unsecured guarantee of €6,122 million (same amount as of December 31, 2012) given by Eni SpA to Treno Alta Velocità – TAV SpA (now RFI – Rete Ferroviaria Italiana SpA) for the proper and timely completion of a project relating to the Milan-Bologna fast-track railway by CEPAV Uno (Consorzio Eni per l’Alta Velocità); consortium members, excluding entities controlled by Eni, gave Eni liability of surety letters and bank guarantees amounting to 10% of their respective portion of the work; (ii) unsecured guarantees and other guarantees given to banks in relation to loans and lines of credit received for €253 million (€828 million at December 31, 2012); the contract released by Eni SpA on behalf of Blue Stream Pipeline Co BV (Eni 50%) to a consortium of international financial institutions (€657 million at December 31, 2012) extinguished in 2013; and (iii) unsecured guarantees and other guarantees given to commissioning entities relating to bid bonds and performance bonds for €62 million (€91 million at December 31, 2012). At December 31, 2013, the underlying commitment covered by such guarantees was €382 million (€456 million at December 31, 2012).

Unsecured and other guarantees given on behalf of third parties of €176 million (€291 million at December 31, 2012) primarily consisted of: (i) guarantees issued on behalf of Gulf LNG Energy and Gulf LNG Pipeline and on behalf of Angola LNG Supply Service Llc (Eni 13.6%) as security against payment commitments of fees in connection with the re-gasification activity (€147 million). The expected commitment has been valued at €147 million (€159 million at December 31, 2012); and (ii) guarantees issued by Eni SpA to banks and other financial institutions in relation to loans and lines of credit for €10 million on behalf of minor investments or companies sold (same amount as of December 31, 2012). At December 31, 2013 the underlying commitment covered by such guarantees was €162 million (€278 million at December 31, 2012).

Commitments and risks

(€ million)

December 31, 2012

December 31, 2013

Commitments

16,247

14,200

Risks

431

377

 

16,678

14,577

Other commitments of €14,200 million (€16,247 million at December 31, 2012) related to: (i) parent company guarantees that were issued in connection with certain contractual commitments for hydrocarbon exploration and production activities and quantified, on the basis of the capital expenditures to be incurred, to €9,804 million (€11,260million at December 31, 2012); (ii) a commitment entered into by Eni USA Gas Marketing Llc on behalf of Angola LNG Supply Service Llc for the acquisition of re-gasified gas at the Pascagoula plant (USA). The expected commitment has been estimated at €2,228 million (€2,613 million at December 31, 2012) and it has included in the off-balance sheet contractual commitments in the following paragraph “Liquidity risk”; (iii) a commitment entered into by Eni USA Gas Marketing Llc on behalf of Gulf LNG Energy for the acquisition of re-gasification capacity at the Pascagoula terminal (6 bcm/y) over a twenty-year period (until 2031). The expected commitment has been estimated at €1,059 million (€1,167 million at December 31, 2012) and it has been included in the off-balance sheet contractual commitments in the following paragraph “Liquidity risk”; (iv) a commitment entered into by Eni USA Gas Marketing Llc on behalf of Cameron LNG Llc, a company belonging to Sempra Group, for the acquisition of re-gasification capacity at the Cameron plant (USA) (6 bcm/y) over a twenty-year period (until 2029). The expected commitment has been estimated at €852 million (€946 million at December 31, 2012) and it has been included in the off-balance sheet contractual commitments in the following paragraph “Liquidity risk”. In February 2014, Sempra obtained the authorization the competent US Authorities to export LNG, while the authorization to convert the terminal into a LNG plant is still pending. In this case Eni would be enabled to exercise an early termination of the contract, significantly reducing future purchase commitments provided for by the original contract; (v) a memorandum of intent signed with the Basilicata Region, whereby Eni has agreed to invest €138 million in the future, also on account of Shell Italia E&P SpA, in connection with Eni’s development plan of oil fields in Val d’Agri (€139 million at December 31, 2012). The commitment has been included in the off-balance sheet contractual commitments in the following paragraph “Liquidity risk”; and (vi) a commitment entered into by Eni USA Gas Marketing Llc for the contract of gas transportation from the Cameron plant (USA) to the American network over a twenty-year period (until 2029). The expected commitment has been estimated at €90 million (€100 million at December 31, 2012) and it has been included in the off-balance sheet contractual commitments in the following paragraph “Liquidity risk”.

Risks of €377 million (€431 million at December 31, 2012) primarily concerned potential risks associated with: (i) the value of assets of third parties under the custody of Eni for €90 million (€123 million at December 31, 2012) (ii) contractual assurances given to acquirers of certain investments and businesses of Eni for €287 million (€308 million at December 31, 2012).

Non-quantifiable commitments

A parent company guarantee was issued on behalf of CARDÓN IV (Eni’s interest 50%), a joint venture operating in the Perla oilfield located in Venezuela, for the supplying to PDVSA GAS of gas quantities until 2036 (end of the concession agreement). At December 31, 2012, the commitment amounted to a maximum of $800 million corresponding for Eni to the maximum amount of the penalty clause provided for in case of an unilateral and anticipated resolution of the supply contract. Eni replaced such guarantee in March 2013, as a consequence of ongoing contract renegotiations. In particular, the penalty clause for unilateral anticipated resolution and, consequently, the maximum value of the guarantee will be determined by applying the local legislation in case of non-fulfilment. The valorisation of the gas to be provided for by Eni amounted to a total of $11 billion. As well as not corresponding to an effective evaluation of the guarantee issued, such amount represents the maximum exposure risk for Eni. A similar guarantee was issued to Eni by PDVSA relating to the fulfilment of the commitments relating to the gas quantities to be collected by PDVSA GAS.

Following the integration signed on April 19, 2011, Eni confirmed to RFI – Rete Ferroviaria Italiana SpA its commitment, previously assumed under the convention signed with Treno Alta Velocità – TAV SpA (now RFI – Rete Ferroviaria Italiana SpA) on October 15, 1991, to guarantee a correct and timely execution of the section Milano-Brescia of the high-speed railway from Milan to Verona. Such integration provides for CEPAV (Consorzio Eni per l’Alta Velocità) Due to act as General Contractor. In order to pledge the guarantee given, the regulation of CEPAV Due binds the associates to give proper sureties and guarantees on behalf of Eni.

Eni is liable for certain non-quantifiable risks related to contractual assurances given to acquirers of certain of Eni’s assets, including businesses and investments, against certain contingent liabilities deriving from tax, social security contributions, environmental issues and other matters applicable to periods during which such assets were operated by Eni. Eni believes such matters will not have a material adverse effect on Eni’s results of operations and liquidity.

Risk factors

Financial risks

Financial risks are those connected with market, credit and liquidity.

Management of financial risks is based on guidelines issued centrally aiming at adapting and coordinating Eni policies on financial risks matters (“Guidelines on financial risks management and control”). The basis of this policy is the pooled and integrated management of commodity risks and the development of asset backed trading activities for optimizing Eni’s exposure to such risks.

Market risk

Market risk is the possibility that changes in currency exchange rates, interest rates or commodity prices will adversely affect the value of the Group’s financial assets, liabilities or expected future cash flows. The Company actively manages market risk in accordance with a set of policies and guidelines that provide a centralized model of handling finance, treasury and risk management operations based on the Company’s departments of operational finance: the parent company’s (Eni SpA) finance department, Eni Finance International, Eni Finance USA and Banque Eni, which is subject to certain bank regulatory restrictions preventing the Group’s exposure to concentrations of credit risk, and Eni Trading & Shipping, that is in charge to execute certain activities relating to commodity derivatives. In particular Eni SpA and Eni Finance International manage subsidiaries’ financing requirements in and outside Italy, respectively, covering funding requirements and using available surpluses. All transactions concerning currencies and derivative contracts on interest rates and currencies are managed by the parent company, including the negotiation of emission trading certificates. The commodity risk of each business unit (Eni’s Divisions or subsidiaries) is pooled and managed by the Midstream Department, while Eni Trading & Shipping executes the negotiation of commodity derivatives. Eni Trading & Shipping SpA and Eni SpA perform trading activities in financial derivatives on external trading venues, such as European and non-European regulated markets, Multilateral Trading Facility (MTF) or similar and brokerage platforms (i.e. SEF), and over the counter on a bilateral basis with external counterparties. Other legal entities belonging to Eni that require financial derivatives enter into these operations through Eni Trading & Shipping SpA and Eni SpA on the basis of the relevant asset class expertises. Eni uses derivative financial instruments (derivatives) in order to minimize exposure to market risks related to fluctuations in exchange rates relating to those transactions denominated in a currency other than the functional currency (the Euro) and interest rates, as well as to optimize exposure to commodity prices fluctuations taking into account the currency in which commodities are quoted. Eni monitors every activity in derivatives classified as risk-reducing (in particular, Back to Back activities, Flow Hedging activities, Asset Backed Hedging activities and Portfolio Management activities) directly or indirectly related to covered industrial assets, so as to effectively optimize the risk profile to which Eni is exposed or could be exposed. If the result of the monitoring shows that derivatives should not be considered as risk-reducing, these derivatives are reclassified in proprietary trading. As the proprietary trading is considered separately from the other activities, its exposure is subject to specific controls, both in terms of VaR and Stop Loss, and in terms of nominal gross value. For Eni, the gross nominal value of proprietary trading activities is compared with the limits set by the relevant international standards.

The framework defined by Eni’s policies and guidelines prescribes that measurement and control of market risk be performed on the basis of maximum tolerable levels of risk exposure defined in terms of limits of stop loss, which expresses the maximum tolerable amount of losses associated with a certain portfolio of assets over a pre-defined time horizon, or in accordance with value at risk techniques. These techniques make a statistical assessment of the market risk on the Group’s activity, i.e. potential gain or loss in fair values, due to changes in market conditions taking account of the correlation existing among changes in fair value of existing instruments. Eni’s finance department defines the maximum tolerable levels of risk exposure to changes in interest rates and foreign currency exchange rates in terms of value at risk, pooling Group companies’ risk positions.

Eni’s calculation and measurement techniques for interest rate and foreign currency exchange rate risks are in accordance with banking standards, as established by the Basel Committee for bank activities surveillance. Tolerable levels of risk are based on a conservative approach, considering the industrial nature of the company. Eni’s guidelines prescribe that Eni Group companies minimize such kinds of market risks by transferring risk exposure to the parent company finance department.

Eni’s guidelines define rules to manage the commodity risk aiming at optimizing core activities and pursuing preset targets of stabilizing industrial and commercial margins. The maximum tolerable level of risk exposure is defined in terms of value at risk and stop loss in connection with exposure deriving from commercial activities and from Asset Backed Trading activities as well as exposure deriving from proprietary trading executed by the subsidiary Eni Trading & Shipping. Internal mandates to manage the commodity risk provide for a mechanism of allocation of the Group maximum tolerable risk level to each business unit. In this framework, Eni Trading & Shipping, in addition to managing risk exposure associated with its own commercial activity and proprietary trading, pools the Midstream Department requests for negotiating commodity derivatives and execute them on the marketplace.

Following the cash inflow from the disposal of the Snam group, Eni decided to retain a cash reserve according to the provisions of the financial plan on the safeguard of assets, cash availability and optimization of return from strategic cash. The management of strategic cash represents for Eni a new type of market risk, i.e. the price risk of strategic cash. This type of risk is part of the management of strategic cash pursued through transactions on own risk in view of optimizing financial returns, while respecting authorized risk levels, safeguarding the Company’s assets and retaining quick access to liquidity.

The four different market risks, whose management and control have been summarized above, are described below.

Exchange rate risk

Exchange rate risk derives from the fact that Eni’s operations are conducted in currencies other than the euro (mainly the US dollar). Revenues and expenses denominated in foreign currencies may be significantly affected by exchange rates fluctuations due to conversion differences on single transactions arising from the time lag existing between execution and definition of relevant contractual terms (economic risk) and conversion of foreign currency-denominated trade and financing payables and receivables (transactional risk). Exchange rate fluctuations affect the Group’s reported results and net equity as financial statements of subsidiaries denominated in currencies other than the euro are translated from their functional currency into euro. Generally, an appreciation of the US dollar versus the euro has a positive impact on Eni’s results of operations, and vice versa. Eni’s foreign exchange risk management policy is to minimize transactional exposures arising from foreign currency movements and to optimize exposures arising from commodity risk. Eni does not undertake any hedging activity for risks deriving from the translation of foreign currency denominated profits or assets and liabilities of subsidiaries which prepare financial statements in a currency other than the euro, except for single transactions to be evaluated on a case-by-case basis. Effective management of exchange rate risk is performed within Eni’s central finance department which pools Group companies’ positions, hedging the Group net exposure through the use of certain derivatives, such as currency swaps, forwards and options. Such derivatives are evaluated at fair value on the basis of market prices provided by specialized info-providers. Changes in fair value of those derivatives are normally recognized through profit and loss as they do not meet the formal criteria to be recognized as hedges in accordance with IAS 39. The VaR techniques are based on variance/covariance simulation models and are used to monitor the risk exposure arising from possible future changes in market values over a 24-hour period within a 99% confidence level and a 20-day holding period.

Interest rate risk

Changes in interest rates affect the market value of financial assets and liabilities of the company and the level of finance charges. Eni’s interest rate risk management policy is to minimize risk with the aim to achieve financial structure objectives defined and approved in the management’s finance plans. Borrowing requirements of Group companies are pooled by the Group’s central finance department in order to manage net positions and the funding of portfolio developments consistently with management’s plans while maintaining a level of risk exposure within prescribed limits. Eni enters into interest rate derivative transactions, in particular interest rate swaps, to effectively manage the balance between fixed and floating rate debt. Such derivatives are evaluated at fair value on the basis of market prices provided from specialized sources. Changes in fair value of those derivatives are normally recognized through the profit and loss account as they do not meet the formal criteria to be accounted for under the hedge accounting method in accordance with IAS 39. Value at risk deriving from interest rate exposure is measured daily on the basis of a variance/covariance model, with a 99% confidence level and a 20-day holding period.

Commodity risk

Eni’s results of operations are affected by changes in the prices of commodities. A decrease in oil and gas prices generally has a negative impact on Eni’s results of operations and vice versa, and may jeopardize the achievement of the financial targets preset in the Company’s plans and budget.

The commodity price risk arises in connection with the following exposures:

  1. Strategic exposure: exposures directly identified by the Board of Directors as a result of strategic investment decisions or outside the planning horizon of risk. These exposures include those associated with the program for the production of proved and unproved oil and gas reserves, long-term gas supply contracts for the portion not balanced by ongoing or highly probable sale contracts, refining margins identified by the Board of Directors as of strategic nature (the remaining volumes can be allocated to the active management of the margin or to asset-backed hedging activities) and minimum compulsory stocks.
  2. Commercial exposure: includes the exposures related to the components underlying the contractual arrangements of industrial and commercial activities and, if related to take-or-pay commitments, to the components related to the time horizon of the four-year plan and budget and the relevant activities of risk management. Commercial exposures are characterized by a systematic risk management activity conducted on the basis of risk/return assumptions by implementing one or more strategies and subjected to specific risk limits (VaR, Stop Loss). In particular, the commercial exposures include exposures subjected to asset-backed hedging activities, arising from the flexibility/optionality of assets.
  3. Proprietary trading exposure: includes operations independently conducted for profit purposes in the short-term, and normally not finalized to the delivery, both within the commodity and financial markets, with the aim to obtain a profit upon the occurrence of a favorable result in the market, in accordance with specific limits of authorized risk (VaR, Stop Loss). In the proprietary trading exposures are included the origination activities, if not connected to contractual or physical assets.

Strategic risk is not subject to systematic activity of management/coverage that is eventually carried out only in case of specific market or business conditions. Because of the extraordinary nature, hedging activities related to strategic risks are delegated to the top management. Strategic risk is subject to measuring and monitoring but is not subject to specific risk limits. If previously authorized by the Board of Directors, exposures related to strategic risk can be used in combination with other commercial exposures in order to exploit opportunities for natural compensation between the risks (natural hedge) and consequently reduce the use of derivatives (by activating logics of internal market).

Eni manages exposure to commodity price risk arising in normal trading and commercial activities in view of achieving stable economic results.

The commodity risk and the exposure to commodity prices fluctuations embedded in commodities quoted in currencies other than the euro at each business unit (Eni’s Divisions or subsidiaries) is pooled and managed by the Portfolio Management unit of the Midstream department for commodities, and by Eni’s finance department for exchange rate requirements. The Midstream department manages business units’ risk exposures to commodities, pooling and optimizing Group companies’ exposures and hedging net exposures on the trading venues through the Trading unit of Eni Trading & Shipping. In order to manage commodity price risk, Eni uses derivatives traded on the organized markets of ICE and NYMEX (futures) and derivatives traded over the counter (swaps, forward, contracts for differences and options) with the underlying commodities being crude oil, refined products or electricity. Such derivatives are evaluated at fair value on the basis of market prices provided from specialized sources or, absent market prices, on the basis of estimates provided by brokers or suitable evaluation techniques. Value at risk deriving from commodity exposure is measured daily on the basis of a historical simulation technique, with a 95% confidence level and a one-day holding period.

Price risk of the strategic liquidity

Market risk deriving from liquidity management is identified as the possibility that changes in prices of financial instruments (bonds, money market instruments and mutual funds) would impact the value of these instruments when evaluated at fair value. In order to manage the investment activity of the strategic liquidity, Eni defined a specific investment policy with aims and constraints in terms of financial activities and operational boundaries, as well as governance guidelines regulating management and control systems. The setting up and maintenance of a reserve of liquidity is mainly aimed to: (i) guarantee of financial flexibility. Liquidity should allow Eni Group to fund any extraordinary need (such as difficulty in access to credit, exogenous shock, macroeconomic environment, as well as merger and acquisitions); (ii) maintain/improve the current credit rating by strengthening balance sheet structure, as well as the concurrent availability of a liquidity reserve which will meet the requirements of rating agencies.

Strategic liquidity management is regulated in terms of Value at Risk (measured on the basis of a historical simulation technique, with a one-day holding period and a 99% confidence level), Stop Loss and other operating limits in terms of concentration, duration, ratings, liquidity and instruments to invest on. Financial leverage or short selling are not allowed. Activities in terms of strategic liquidity management started in the second half of the year.

The following table shows amounts in terms of value at risk, recorded in 2013 (compared with 2012) relating to interest rate and exchange rate risks in the first section, and commodity risk in the second section.

(Value at risk – parametric method variance/covariance; holding period: 20 days; confidence level: 99%)

 

2012

2013

(€ million)

High

Low

Average

At year end

High

Low

Average

At year end

(1)

Value at risk deriving from interest and exchange rates exposures include the following finance department: Eni Corporate Treasury Department, Eni Finance International, Banque Eni and Eni Finance USA.

Interest rate (1)

8.69

1.41

3.13

1.88

3.67

1.49

2.07

2.15

Exchange rate (1)

1.31

0.12

0.44

0.19

0.37

0.07

0.14

0.24

(Value at risk – Historic simulation weighted method; holding period: 1 day; confidence level: 95%)

 

2012

2013

(€ million)

High

Low

Average

At year end

High

Low

Average

At year end

(1)

Refers to the Midstream Department (risk exposure from Refining & Marketing Division and Gas & Power Division), Versalis, Eni Trading & Shipping BV (Amsterdam) and the subsidiaries outside Italy pertaining to the Division.

(2)

Cross-commodity propietary trading, both for commodity contracts and financial derivatives, refers to Eni Trading & Shipping SpA (London-Bruxelles-Singapore) and Eni Trading & Shipping Inc (Houston).

Commercial exposures - Management Portfolio (1)

84.20

35.65

59.61

40.99

108.13

36.59

59.92

66.44

Trading (2)

5.88

1.11

2.80

1.24

7.50

1.36

4.11

2.93

(Value at risk – Historic simulation method; holding period: 1 day; confidence level: 99%)

 

2012

2013

(€ million)

High

Low

Average

At year end

High

Low

Average

At year end

(1)

The management of the strategic liquidity portfolio started from July 2013.

Strategic liquidity (1)

 

 

 

 

1.07

0.32

0.89

0.92

Credit risk

Credit risk is the potential exposure of the Group to losses in case counterparties fail to perform or pay amounts due. The Group manages differently credit risk depending on whether credit risk arises from exposure to financial counterparties or to customers relating to outstanding receivables. Individual business units and Eni’s corporate financial and accounting units are responsible for managing credit risk arising in the normal course of the business. The Group has established formal credit systems and processes to ensure that before trading with a new counterpart can start, its creditworthiness is assessed. Also credit litigation and receivable collection activities are assessed. Eni’s corporate units define directions and methods for quantifying and controlling customer’s reliability. With regard to risk arising from financial counterparties deriving from current and strategic use of liquidity, Eni has established guidelines prior to entering into cash management and derivative contracts to assess the counterparty’s financial soundness and rating in view of optimizing the risk profile of financial activities while pursuing operational targets. Maximum limits of risk exposure are set in terms of maximum amounts of credit exposures for categories of counterparties as defined by the Company’s Board of Directors taking into account the credit ratings provided by primary credit rating agencies on the marketplace. Credit risk arising from financial counterparties is managed by the Group operating finance department, including Eni’s subsidiary Eni Trading & Shipping which specifically engages in commodity derivatives transactions and by Group companies and Divisions, only in the case of physical transactions with financial counterparties consistently with the Group centralized finance model. Eligible financial counterparties are closely monitored to check exposures against limits assigned to each counterparties on a daily basis.

Liquidity risk

Liquidity risk is the risk that suitable sources of funding for the Group may not be available, or the Group is unable to sell its assets on the marketplace in order to meet short-term finance requirements and to settle obligations. Such a situation would negatively impact Group results as it would result in the Company incurring higher borrowing expenses to meet its obligations or under the worst of conditions the inability of the Company to continue as a going concern. As part of its financial planning process, Eni manages the liquidity risk by targeting such a capital structure as to allow the Company to maintain a level of liquidity adequate to the Group’s needs, optimizing the opportunity cost of maintaining liquidity reserves also achieving an efficient balance in terms of maturity and composition of finance debt. For this purpose, Eni holds a significant amount of liquidity reserve (financial assets plus committed credit lines), which aims to (a) deal with identified risk factors that could significantly affect the cash flow expected in the Financial Plan (i.e. changes in the scenario and/or production volumes, delays in disposals, limitations in profitable acquisitions), (b) ensure a full coverage of short-term debt and the coverage of medium and long-term debts with a maturity of 24 months, even in case of restrictions to the credit access, (c) ensuring the availability of an adequate level of financial flexibility to support the Group’s development plans.

The financial asset reserve will be employed with a short-term profile and fast liquidability, favouring investments with very low risk profile.

At present, the Group believes to have access to sufficient funding to meet the current foreseeable borrowing requirements as a consequence of the availability of financial assets and lines of credit and the access to a wide range of funding at competitive costs through the credit system and capital markets.

Eni has in place a program for the issuance of Euro Medium Term Notes up to €15 billion, of which about €13.7 billion were drawn as of December 31, 2013.

The Group has credit ratings of A and A-1 respectively for long and short-term debt assigned by Standard & Poor’s and A3 and P-2 assigned by Moody’s; the outlook is negative in both ratings. Eni’s credit rating is linked in addition to the Company’s industrial fundamentals and trends in the trading environment to the sovereign credit rating of Italy. On the basis of the methodologies used by Standard & Poor’s and Moody’s, a potential downgrade of Italy’s credit rating may trigger a potential knock-on effect on the credit rating of Italian issuers such as Eni and make it more likely that the credit rating of the notes or other debt instruments issued by the Company could be downgraded. Eni, through the constant monitoring of the international economic environment and continuing dialogue with financial investors and rating agencies, believes to be ready to perceive emerging critical issues screened by the financial community and to be able to react quickly to any changes in the financial and the global macroeconomic environment and implement the necessary actions to mitigate such risks, coherently with Company strategies.

In the course of 2013, Eni issued bonds for a total amount of €4.3 billion, of which €3.1 billion related to the Euro Medium Term Notes Program and €1.2 billion related to bonds exchangeable into Snam ordinary shares.

At December 31, 2013, Eni maintained short-term committed and uncommitted unused borrowing facilities of €14.3 billion, of which €2.1 billion were committed, and long-term committed borrowing facilities of €4.7 billion which were completely undrawn at the balance sheet date. These facilities bore interest rates and fees for unused facilities that reflected prevailing market conditions.

The tables below summarize the Group main contractual obligations (undiscounted) for finance debt repayments, including expected payments for interest charges, and trade and other payables maturities outstanding at period end.

Finance debt repayments including expected payments for interest charges and derivatives

The tables below summarize the Group main contractual obligations for finance debt repayments, including expected payments for interest charges and derivatives.

 

Maturity year

(€ million)

2013

2014

2015

2016

2017

2018 and thereafter

Total

December 31, 2012

 

 

 

 

 

 

 

Non-current liabilities

2,555

2,090

3,941

2,180

2,956

8,275

21,997

Current financial liabilities

2,223

 

 

 

 

 

2,223

Fair value of derivative instruments

925

132

89

2

11

50

1,209

 

5,703

2,222

4,030

2,182

2,967

8,325

25,429

Interest on finance debt

840

725

622

550

465

1,491

4,693

Guarantees to banks

212

 

 

 

 

 

212

 

 

 

 

 

 

 

 

 

Maturity year

(€ million)

2014

2015

2016

2017

2018

2019 and thereafter

Total

December 31, 2013

 

 

 

 

 

 

 

Non-current liabilities

1,757

3,713

3,224

2,951

1,406

9,841

22,892

Current financial liabilities

2,742

 

 

 

 

 

2,742

Fair value of derivative instruments

996

243

1

5

 

34

1,279

 

5,495

3,956

3,225

2,956

1,406

9,875

26,913

Interest on finance debt

821

712

651

558

430

1,698

4,870

Guarantees to banks

254

 

 

 

 

 

254

Trade and other payables

The tables below summarize the Group trade and other payables by maturity.

 

Maturity year

(€ million)

2013

2014-2017

2018 and thereafter

Total

December 31, 2012

 

 

 

 

Trade payables

14,993

 

 

14,993

Other payables and advances

8,588

19

38

8,645

 

23,581

19

38

23,638

 

 

 

 

 

 

Maturity year

(€ million)

2014

2015-2018

2019 and thereafter

Total

December 31, 2013

 

 

 

 

Trade payables

15,529

 

 

15,529

Other payables and advances

8,069

18

57

8,144

 

23,598

18

57

23,673

Expected payments by period under contractual obligations and commercial commitments

The Group has in place a number of contractual obligations arising in the normal course of the business. To meet these commitments, the Group will have to make payments to third parties. The Company’s main obligations pertain to take-or-pay clauses contained in the Company’s gas supply contracts or shipping arrangements, whereby the Company obligations consist of off-taking minimum quantities of product or service or, in case of failure, paying the corresponding cash amount that entitles the Company the right to off-take the product or the service in future years. Future obligations in connection with these contracts were calculated by applying the forecasted prices of energy or services included in the four-year business plan approved by the Company’s Board of Directors. The table below summarizes the Group principal contractual obligations as of the balance sheet date, shown on an undiscounted basis.

 

Maturity year

(€ million)

2014

2015

2016

2017

2018

2019 and thereafter

Total

(a)

Operating leases primarily regarded assets for drilling activities, time charter and long-term rentals of vessels, lands, service stations and office buildings. Such leases did not include renewal options. There are no significant restrictions provided by these operating leases which limit the ability of the Company to pay dividend, use assets or to take on new borrowings.

(b)

Represents the estimated future costs for the decommissioning of oil and natural gas production facilities at the end of the producing lives of fields, well-plugging, abandonment and site restoration.

(c)

Environmental liabilities do not include the environmental charge of 2010 amounting to €1,109 million for the proposal to the Italian Ministry for the Environment to enter into a global transaction related to nine sites of national interest because the dates of payment are not reasonably estimable.

(d)

Represents any agreement to purchase goods or services that is enforceable and legally binding and that specifies all significant terms.

(e)

Mainly refers to arrangements to purchase capacity entitlements at certain re-gasification facilities in the US (€1,911 million).

Operating lease obligations (a)

706

423

335

263

191

349

2,267

Decommissioning liabilities (b)

214

162

206

304

331

13,125

14,342

Environmental liabilities (c)

279

329

246

126

114

622

1,716

Purchase obligations (d)

21,304

20,307

17,947

16,437

15,508

150,867

242,370

- Gas

 

 

 

 

 

 

 

- take-or-pay contracts

18,228

18,724

16,427

14,967

14,277

143,912

226,535

- ship-or-pay contracts

1,903

1,322

1,272

1,232

998

5,037

11,764

- Other take-or-pay or ship-or-pay obligations

130

125

118

109

104

480

1,066

- Other purchase obligations (e)

1,043

136

130

129

129

1,438

3,005

Other obligations

3

3

3

3

3

123

138

- Memorandum of intent relating Val d’Agri

3

3

3

3

3

123

138

 

22,506

21,224

18,737

17,133

16,147

165,086

260,833

Capital expenditure commitments

In the next four years Eni plans to make capital expenditures of €53.8 billion. The table below summarizes Eni’s capital expenditure commitments for property, plant and equipment and capital projects. Capital expenditures are considered to be committed when the project has received the appropriate level of internal management approval. At this stage, procurement contracts to execute those projects have already been awarded or are being awarded to third parties.

The amounts shown in the table below include committed expenditures to execute certain environmental projects.

 

Maturity year

(€ million)

2014

2015

2016

2017

2018 and thereafter

Total

Committed on major projects

5,697

5,246

4,908

3,224

17,709

36,784

Other committed projects

7,555

4,902

2,865

1,705

865

17,892

 

13,252

10,148

7,773

4,929

18,574

54,676

Other information about financial instruments

The carrying amount of financial instruments and relevant economic effect as of and for the years ended December 31, 2012 and 2013 consisted of the following:

 

2012

2013

 

 

Finance income (expense) recognized in:

 

Finance income (expense) recognized in:

(€ million)

Carrying amount

Profit and loss account

Equity

Carrying amount

Profit and loss account

Equity

(a)

Income or expense were recognized in the profit and loss account within Finance income (expense).

(b)

In the profit and loss account, economic effects were recognized as loss within "Other operating income (loss)” for €96 million (loss for €157 million in 2012) and as expense within Finance income (expense) for €92 million (expense for €251 million in 2012).

(c)

Income was recognized in the profit and loss account within "Income (expense) from investments" for €2,158 million (income for €1,247 million in 2012) and within "Net profit (loss) for the period - Discontinued operations" for €3,470 million.

(d)

In the profit and loss account, economic effects were essentially recognized as expense within "Purchase, services and other" for €311 million (expense for €25 million in 2012) (impairments net of reversal) and as income for €34 million within "Finance income (expense)" (expense for €29 million in 2012) (exchange rate differences at year-end and amortized cost).

(e)

In the profit and loss account, exchange differences arising from accounts denominated in foreign currency and translated into euro at year-end were primarily recognized within "Finance income (expense)".

(f)

In the profit and loss account, income or expense were recognized within "Net sales from operations" and "Purchase, services and other" as expense for €526 million (expense for €289 million at December 31, 2012) and as income within "Finance income (expense)" for €25 million (expense for €1 million in 2012) (time value component).

Held-for-trading financial instruments

 

 

 

 

 

 

Securities (a)

 

 

 

5,004

4

 

Non-hedging derivatives (b)

183

(395)

 

(22)

(180)

 

Trading derivatives (b)

3

(13)

 

(61)

(8)

 

Held-to-maturity financial instruments

 

 

 

 

 

 

Securities (a)

69

1

 

80

1

 

Available-for-sale financial instruments

 

 

 

 

 

 

Securities (a)

235

8

16

235

7

(1)

Investments valued at fair value

 

 

 

 

 

 

Other non-current investments (c)

4,782

4,717

141

2,770

456

(64)

Other non-current investments - Held for sale investments (c)

 

 

 

2,131

1,702

 

Receivables and payables and other assets/liabilities valued at amortized cost

 

 

 

 

 

 

Trade receivables and other (d)

28,039

(54)

 

28,799

(277)

 

Financing receivables (a)

2,981

70

 

2,141

11

 

Trade payables and other (e)

23,638

104

 

23,673

28

 

Financing payables (a)

24,463

(831)

 

25,879

(845)

 

Net assets (liabilities) for hedging derivatives (f)

(17)

(290)

 

(202)

(501)

 

Disclosures about the offsetting of financial instruments

The table below summarizes the disclosures about the offsetting of financial instruments.

(€ million)

Gross amount of financial assets and liabilities

Gross amount of financial assets and liabilities subject to offsetting

Net amount of financial assets and liabilities

December 31, 2012

 

 

 

Financial assets

 

 

 

Trade and other receivables

29,853

1,106

28,747

Financial liabilities

 

 

 

Trade and other liabilities

24,687

1,106

23,581

 

 

 

 

December 31, 2013

 

 

 

Financial assets

 

 

 

Trade and other receivables

30,468

1,395

29,073

Other current assets

1,620

295

1,325

Other non-current assets

3,718

35

3,683

Financial liabilities

 

 

 

Trade and other liabilities

24,993

1,395

23,598

Other current liabilities

1,752

304

1,448

Other non-current liabilities

1,730

26

1,704

The offsetting of financial assets and liabilities of €1,725 million (€1,106 million at December 31, 2012) related for €1,084 million (€1,047 million at December 31, 2012) the offsetting of receivables and debts pertaining to the Exploration & Production segment towards state entities.

Disclosures on fair value of financial instruments

Following the classification of financial assets and liabilities, measured at fair value in the balance sheet, is provided according to the fair value hierarchy defined on the basis of the relevance of the inputs used in the measurement process. In particular, on the basis of the features of the inputs used in making the measurements, the fair value hierarchy shall have the following levels:

  1. Level 1: quoted prices (unadjusted) in active markets for identical financial assets or liabilities;
  2. Level 2: measurements based on the basis of inputs, other than quoted prices above, which, for assets and liabilities that have to be measured, can be observable directly (e.g. prices) or indirectly (e.g. deriving from prices);
  3. Level 3: inputs not based on observable market data.

Financial instruments measured at fair value in the balance sheet as of at December 31, 2013, were classified as follows: (i) Level 1 “Quoted financial assets held for trading”, “Financial assets available for sale”, “Inventories – Certificates and emission rights”, “Derivatives – Futures” and “Other investments” valued at fair value; and (ii) Level 2, derivative instruments different from “Non-quoted financial assets held for trading”, “Derivative financial instruments other than futures” included in “Other current assets”, “Other non-current assets”, “Other current liabilities” and “Other non-current liabilities”. During 2013, there were no transfers between the different hierarchy levels of fair value.

The table below summarizes the amount of financial instruments valued at fair value:

(€ million)

Note

December 31, 2012

December 31, 2013

 

 

Level 1

Level 2

Level 1

Level 2

Current assets

 

 

 

 

 

Quoted financial assets held for trading

(8)

 

 

4,461

 

Non-quoted financial assets held for trading

(8)

 

 

 

543

Financial assets available for sale

(9)

235

 

235

 

Inventories - Certificates and emission rights

(11)

19

 

22

 

Derivatives - Futures

(14)

26

 

64

 

Cash flow hedge derivatives

(14)

 

31

 

14

Non-hedging and trading derivatives

(14)

 

890

 

654

Non-current assets

 

 

 

 

 

Other investments valued at fair value

(18)

4,782

 

2,770

 

Other investments held for sale valued at fair value

(32)

 

 

 

2,131

Derivatives - Futures

(21)

5

 

 

 

Cash flow hedge derivatives

(21)

 

2

 

6

Non-hedging derivatives

(21)

 

424

 

256

Current liabilities

 

 

 

 

 

Derivatives - Futuress

(26)

12

 

12

 

Cash flow hedge derivatives

(26)

 

32

 

213

Non-hedging and trading derivatives

(26)

 

881

 

771

Non-current liabilities

 

 

 

 

 

Non-hedging derivatives - Futures

(31)

1

 

 

 

Cash flow hedge derivatives

(31)

 

13

 

1

Non-hedging derivatives

(31)

 

270

 

282

Legal proceedings

Eni is a Party to a number of civil actions and administrative arbitral and other judicial proceedings arising in the ordinary course of business.

Based on information available to date, and taking into account the existing risk provisions, Eni believes that the foregoing will not have an adverse effect on Eni’s Consolidated Financial Statements. The following is a description of the most significant proceedings currently pending. Unless otherwise indicated below, no provisions have been made for these legal proceedings as Eni believes that negative outcomes are not probable or because the amount of the provision cannot be estimated reliably.

1. Environment

1.1 Criminal proceedings in the matters of environment, health and safety

  1. Fatal accident Truck Center Molfetta – Prosecuting body: Public Prosecutor of Trani. On May 11, 2010, Eni SpA, eight employees of the Company and a former employee were notified of closing of the investigation into alleged manslaughter, grievous bodily harm and illegal disposal of waste materials in relation to a fatal accident occurred in March 2008 that caused the death of four workers deputed to the cleaning of a tank car owned by a company part of the Italian Railways Group. The tank was used for the transportation of liquid sulphur produced by Eni in the Refinery of Taranto. The Public Prosecutor has removed three defendants and transmitted evidence to the Judge for the Preliminary Investigations requesting to dismiss the proceeding. The Judge for the Preliminary Investigations accepted the above mentioned request. In the hearing of April 19, 2011, the Judge admitted as plaintiffs against the above mentioned individuals all the parts, excluding the relatives of one of the victims, whose position has been declared inadmissible lacking of cause of action. The Judge declared inadmissible all the requests brought by other parties to act as plaintiffs against Eni. On December 5, 2011, the Judge pronounced an acquittal sentence for the individuals involved and for Eni SpA, as the indictment is groundless. The first hearing of the appeal filed by the Public Prosecutor has not been scheduled yet.

  2. Syndial SpA (company incorporating EniChem Agricoltura SpA – Agricoltura SpA in liquidation – EniChem Augusta Industriale Srl – Fosfotec Srl) – Proceeding about the industrial site of Crotone. A criminal proceeding is pending before the Public Prosecutor of Crotone relating to allegations of environmental disaster, poisoning of substances used in the food chain and omitted clean-up due to the activity at a landfill site which was taken over by Eni’s subsidiary in 1991 following the divestment of an industrial complex by Montedison (now Edison SpA). The landfill site had been filled with industrial waste from Montedison activities till 1989 and then no additional waste was discharged there. Eni’s subsidiary carried out the clean-up of the landfill in 1999 through 2000. The defendants are certain managers at Eni’s subsidiaries which have owned and managed the landfill since 1991. At the conclusion of the analysis conducted by the experts, the documents were returned to the Public Prosecutor of Crotone for further investigations and possible requests of trial.

  3. Eni SpA – Gas & Power Division – Industrial site of Praia a Mare. Based on complaints filed by certain offended persons, the Public Prosecutor of Paola started an enquiry about alleged diseases related to tumours which those persons contracted on the workplace. Those persons were employees at an industrial complex owned by a Group subsidiary many years ago. On the basis of the findings of independent appraisal reports, in the course of 2009 the Public Prosecutor resolved that a number of ex-manager of that industrial complex would stand trial. In the preliminary hearing held in November 2010, 189 persons entered the trial as plaintiff; while 107 persons were declared as having been offended by the alleged crime. The plaintiffs have requested that both Eni and Marzotto SpA would bear civil liability. However, compensation for damages suffered by the offended persons has yet to be determined. Upon conclusion of the preliminary hearing, the Public Prosecutor resolved that all defendants would stand trial for culpable manslaughter, culpable injuries, environmental disaster and negligent conduct about safety measures on the workplace. Following a settlement agreement with Eni, Marzotto SpA has entered settlement agreements with all plaintiffs, except for the local administrations. The proceeding is pending.

  4. Syndial SpA and Versalis SpA – Porto Torres dock – Prosecuting body: Public Prosecutor of Sassari. On July 2012, the Judge for the Preliminary Hearing, following a request of the Public Prosecutor of Sassari, requested the performance of a probationary evidence relating to the functioning of the hydraulic barrier of Porto Torres site (ran by Syndial SpA) and its capacity to avoid the dispersion of contamination released by the site in the near portion of sea. Syndial SpA and Versalis SpA have been notified that its chief executive officers and other managers are being investigated.

  5. Syndial SpA – Public Prosecutor of Gela. An investigation before the Public Prosecutor of Gela is pending regarding a number of former Eni employees. In particular the proceeding involves 17 former managers of the companies ANIC SpA, EniChem SpA, EniChem Anic SpA, Anic Agricoltura SpA, Agip Petroli SpA and Praoil Aromatici e Raffinazione Srl who were previously in charge of conducting operations and granting security at Clorosoda plant in Gela. The proceeding regards the crimes of culpable manslaughter and grievous bodily harm related to the death of 12 former employees and alleged diseases which those persons may have contracted at the above mentioned plant. Alleged crimes relate to the period from 1969, when operations on Clorosoda plant have commenced, to 1998, when the clean-up activities have terminated. The Public Prosecutor requested the performance of a medico-legal appraisal on over 100 people employed on the abovementioned plant to verify the relation of causality between the deaths occurred and the eventual pathologies affecting these individuals, and the exposures related to the work performed and missing implementation by the relevant company functions of the measures necessary for ensuring the employee health and security in relation to the risks connected with the mentioned working activities. The proceeding is at a preliminary phase.

  6. Seizure of areas located in the Municipalities of Cassano allo Jonio and Cerchiara di Calabria – Prosecuting body: Public Prosecutor of Castrovillari. Certain areas owned by Eni in the Municipalities of Cassano allo Jonio and Cerchiara di Calabria have been seized by the Judicial Authority pending an investigation about an alleged improper handling of industrial waste from the processing of zinc ferrites at the industrial site of Pertusola Sud, which was subsequently shut down, and illegal storing in the seized areas. The circumstances under investigation are the same considered in a criminal action for alleged omitted clean-up which was concluded in 2008 without any negative outcome on part of Eni’s employees. Eni’s subsidiary Syndial SpA has removed any waste materials from the landfills Syndial entered a transaction agreement with the municipality of Cerchiara to settle all damages caused by the unauthorized landfills to the territory of the Municipality. The municipality of Cerchiara renounced to all claims in relation to the circumstances investigated in the criminal proceeding. Eni’s subsidiary has also arranged a similar transaction with the Municipality of Cassano. The criminal proceeding is still pending.

  7. Syndial SpA – Proceeding on the asbestos at the Ravenna site. A criminal proceeding is pending before the Tribunal of Ravenna about the crimes of culpable manslaughter, injuries and environmental disaster which would have been allegedly committed by former Syndial employees at the site of Ravenna. The site was taken over by Syndial following a number of corporate mergers and acquisitions. The alleged crimes would date back to 1991. In the proceeding there are 75 offended people. The plaintiffs include relatives of the alleged victims and various local administrations and other institutional bodies, including local trade unions. The advocacy of Syndial claimed the statute of limitation about the crime of environmental disaster which would exclude the alleged crimes of manslaughter and injury. On February 6, 2014 the Judge for the Preliminary Hearing at Ravenna decided that all defendants would stand trial and ascertained the statute of limitation only with reference to the alleged crime of culpable injury. The proceeding is entering the hearing phase.

1.2 Civil and administrative proceedings in the matters of environment, health and safety

  1. Syndial SpA (former EniChem SpA) – Summon for alleged environmental damage caused by DDT pollution in the Lake Maggiore – Prosecuting body: Ministry for the Environment. In May 2003, the Ministry for the Environment summoned Syndial (former EniChem) to obtain a sentence condemning the Eni subsidiary to compensate an alleged environmental damage caused by the activity of the Pieve Vergonte plant in the years 1990 through 1996. With a temporarily executive sentence dated July 3, 2008, the District Court of Turin sentenced the subsidiary Syndial SpA to compensate environmental damages amounting to €1,833.5 million, plus legal interests that accrue from the filing of the decision. Syndial and Eni technical-legal consultants have considered the decision and the amount of the compensation to be without factual and legal basis and have concluded that a negative outcome of this proceeding is unlikely. Particularly, Eni and its subsidiary deem the amount of the environmental damage to be absolutely wholly groundless as the sentence has been considered to lack sufficient elements to support such a material amount of the liability charged to Eni and its subsidiary with respect to the volume of pollutants ascertained by the Italian Environmental Minister. Based on these technical-legal advices also supported by external accounting consultants, no provisions have been made against the proceeding. In July 2009, Syndial filed an appeal against the abovementioned sentence, and consequently the proceeding would continue before a second degree court. In the hearing of June 15, 2012, before the Second Degree Court of Turin, the Minister of the Environment, formalized trough the Board of State Lawyers its decision to not execute the sentence until a final verdict on the whole matter is reached.

    The second degree court requested Syndial to stand as defendant and then requested a technical appraisal of the matter. This technical appraisal reached a favourable outcome for Syndial; however such outcome has been questioned by the Board of State Lawyers. The hearing for the discussion of the conclusions has not been scheduled yet.

  2. Action commenced by the Municipality of Carrara for the remediation and reestablishment of previous environmental conditions at the Avenza site and payment of environmental damage. The Municipality of Carrara commenced an action before the Court of Genova requesting Syndial SpA to remediate and restore previous environmental conditions at the Avenza site and the payment of environmental damage (amounting to €139 million), further damages of various types (e.g. damage to the natural beauty of this site) amounting to €80 million as well as damages relating to loss of profit and property amounting to approximately €16 million. This request is related to an accident that occurred in 1984, as a consequence of which EniChem Agricoltura SpA (later merged into Syndial SpA), at the time owner of the site, carried out safety and remediation works. The Ministry for the Environment joined the action and requested environmental damage payment – from a minimum of €53.5 million to a maximum of €93.3 million – to be broken down among the various companies that ran the plant in the past. With a sentence of March 2008, the Court of Genova rejected all claims made by the Municipality of Carrara and the Ministry for the Environment. The Second Instance Court too confirmed the decision issued in the first judgment and rejected all the claims made by the plaintiffs. The Ministry for the Environment filed an appeal before a third instance court on the belief that Syndial is to be held responsible for the environmental damage as the Eni subsidiary took over the site from the previous owners assuming all existing liabilities; it was responsible for managing the plant and inadequately remediating the site after the occurrence of an incident in 1984 and for omitted clean-up. Syndial established itself as defendant. The proceeding is pending.

  3. Ministry for the Environment – Augusta harbor. The Italian Ministry for the Environment with various administrative acts prescribed companies running plants in the petrochemical site of Priolo to perform safety and environmental remediation works in the Augusta harbour. Companies involved include Eni subsidiaries Versalis, Syndial and Eni Refining & Marketing Division. Pollution has been detected in this area primarily due to a high mercury concentration which is allegedly attributed to the industrial activity of the Priolo petrochemical site. The abovementioned companies opposed said administrative actions, objecting in particular to the way in which remediation works have been designed and modes whereby information on pollutants concentration has been gathered. A number of administrative proceedings were started on this matter, which were reunified before the Regional Administrative Court of Catania. In October 2012, said Court ruled in favour of Eni’s subsidiaries against the Ministry prescriptions about the removal of pollutants and the construction of a physical barrier. The Court ruling was based on a sentence filed by the Court of Justice of the European Community. Specifically, the European Court confirmed the EU principle of the liability associated with the environmental damage, while at the same time reaffirming the necessity to ascertain the relation between cause and effect and identify the entity that is actually liable for polluting. It must be noted that the Public Prosecutor of Siracusa commenced a criminal action against unknown persons in order to verify the effective contamination of the Augusta harbour and the risks relating to the execution of the clean-up project proposed by the Ministry. The technical assessment disposed by the Public Prosecutor generated the following outcomes: a) no public health risk in the Augusta harbor; b) absence of any involvement on part of Eni companies in the contamination; and c) drainages dangerousness. Based on those findings, the Public Prosecutor decided to dismiss the proceeding.

  4. Claim for preventive technical inquiry – Court of Gela. In February 2012, Eni’s subsidiaries Raffineria di Gela SpA and Syndial SpA and the parent company Eni SpA (involved in this matter through the operations of the Refining & Marketing Division) were notified a claim issued by 18 parents of children born malformed in the municipality of Gela between 1992 and 2007. The claim for preventive technical inquiry aims at verifying the relation of causality between the malformation pathologies suffered by the children of the plaintiffs and the environmental pollution caused by the Gela site (pollution deriving from the existence and activities at the industrial plants of the Gela Refinery and Syndial SpA), quantifying the alleged damages suffered and eventually identifying the terms and conditions to settle the claim. The examination of the claims filed by the plaintiffs confirmed the lack of evidence in the relation of causality. In any case, the same issue was the subject of previous inquiries in a number of proceedings, all resolved without the ascertainment of any illicit behaviour on part of Eni or its subsidiaries. A technical appraisal of the matter is pending. Furthermore, 15 more claims were notified to Eni’s subsidiaries on the same matter. Those proceedings are ongoing.

  5. Environmental claim relating to the Municipality of Cengio – Plaintiffs: The Ministry for the Environment and the Delegated Commissioner for Environmental Emergency in the territory of the Municipality of Cengio. The Ministry for the Environment and the Delegated Commissioner for Environmental Emergency in the territory of the Municipality of Cengio summoned Eni’s subsidiary Syndial before a Civil Court and sentenced the Eni’s subsidiary to compensate the environmental damage relating to the site of Cengio. The plaintiffs accused Syndial of negligence in performing the clean-up and remediation of the site. On the contrary, Syndial believes to have executed properly and efficiently the clean-up work in accordance with the framework agreement signed with the involved administrations including the Ministry of the Environment in 2000. On February 6, 2013, a Court in Genoa ruled the resumption of the proceeding and established a technical appraisal to verify the existence of the environmental damage. The proceeding is pending.

  6. Syndial SpA and Versalis SpA – Porto Torres – Prosecuting body: Public Prosecutor of Sassari. The Public Prosecutor of Sassari (Sardinia) resolved that a number of officers and senior managers of companies engaging in petrochemicals operations at the site of Porto Torres, including the manager responsible for plant operations of the Company’s fully-owned subsidiary Syndial, would stand trial due to allegations of environmental damage and poisoning of water and crops. The Province of Sassari, the Municipality of Porto Torres and other entities have been acting as plaintiffs. The Judge for the Preliminary Hearing admitted as plaintiffs the above mentioned parts, but based on the exceptions issued by Syndial on the lack of connection between the action as plaintiff and the charge, denied that the claimants would act as plaintiff with regard to the serious pathologies related to the existence of poisoning agents in the marine fauna of the industrial port of Porto Torres. The trial before a jurisdictional body of the Italian criminal law which is charged with judging the most serious crimes, was annulled as that jurisdictional body did not recognize the gravity elements justifying its judgment due to a different crime allegation in the notice of conclusion of the preliminary investigation with respect to the crime allegation presented in the request of trial filed by the Public Prosecutor. In February 2013, the Prosecutor of Sassari has notified the conclusion of preliminary investigations and requested a new imputation for negligent behavior instead of illicit conduct. In the conclusions of the preliminary hearing, the GUP of Sassari dismissed the accusation as a result of the statute of limitations.

    The Public Prosecutor filed an appeal before a Third Instance Court.

  7. Kashagan. On 7 March 2014, the Atyrau Region Environmental Department (“ARED”) launched a series of civil claims against the consortium developing the Kashagan field. These proceedings allege certain emissions associated with gas flaring occurring during commissioning have resulted in infringements of environmental laws and environmental damages. The aggregate value of the civil claims is approximately US$737 million (KZT 134 billion), of which eni’s share would be approximately US$124 million (KZT 22.5 billion). The Kashagan project’s consortium disputes these allegations.

2. Court inquiries and of other Regulatory Authorities

  1. Fos Cavaou. An arbitration proceeding before the International Chamber of Commerce of Paris between the client company Société du Terminal Methanier Fos Cavaou (now FOSMAX LNG) and the contractor STS – a French consortium participated by Saipem SA (50%), Technimont SpA (49%) and Sofregaz SA (1%) – is pending. The memorandum filed by FOSMAX LNG supporting the arbitration proceeding claimed the payment of €264 million for damage payment, delay penalties and costs incurred for the termination of the works. Approximately €142 million of the total amount requested related to loss of profit, which is an item that cannot be compensated based on the existing contractual provisions with the exception of fraudulent and serious culpable behaviour. STS filed counterclaim for a total amount of approximately €338 million as damage repayment due to the alleged excessive interference of FOSMAX LNG in the execution of the works and payment of extra works not recognized by the client. Both parties filed their memoranda. Management expects the arbitration experts to issue a final ruling by the end of 2014.

  2. Eni SpA – Reorganization procedure of the airlines companies Volare Group, Volare Airlines and Air Europe – Prosecuting body: Delegated Commissioner. In March 2009, Eni and its subsidiary Sofid (now Eni Adfin) were notified of a bankruptcy claw back as part of a reorganization procedure filed by the airlines companies Volare Group, Volare Airlines and Air Europe which commenced under the provisions of Ministry of Production Activities, on November 30, 2004. The request regarded the override of all the payments made by those entities to Eni and Eni Adfin, as Eni agent for the receivables collection, in the year previous to the insolvency declaration from November 30, 2003 to November 29, 2004, for a total estimated amount of €46 million plus interest. Eni and Eni Adfin were admitted as defendants. After the conclusion of the investigation, a court ruled against the claims made by the commissioners of the reorganization procedures. The relevant ruling was filed on March 1, 2012. The commissioners filed a counterclaim against the first degree sentence.

  3. Reorganization procedure of Alitalia Linee Aeree Italiane SpA under extraordinary administration. On January 23, 2013, the Italian airline company Alitalia undergoing a reorganization procedure summoned before the Court of Rome Eni, Exxon Italia and Kuwait Petroleum Italia SpA to obtain a compensation for alleged damages caused by a presumed anticompetitive behaviour on part of the three petroleum companies in the supply of jet fuel in the years 1998 through 2009. The claim was based on a deliberation filed by the Italian Antitrust Authority on June 14, 2006. The antitrust deliberation accused Eni and other five petroleum companies of anticompetitive agreements designed to split the market for jet fuel supplies and blocking the entrance of new players in the years 1998 through 2006. The antitrust findings were substantially endorsed by an administrative court. Alitalia has made a claim against the three petroleum companies jointly and severally presenting two alternative ways to assess the alleged damages. A first assessment of the overall damages amounted to €908 million. This was based on the presumption that the anti competitive agreements among the defendants would have prevented Alitalia from autonomously purchasing supplies of jet fuel in the years when the existence of the anti competitive agreements were ascertained by the Italian Antitrust Authority and in subsequent years until Alitalia ceased to operate airline activity. Alitalia asserts the incurrence of higher supply costs of jet fuel of €777 million excluding interest accrued and other items which add to the lower profitability caused by a reduced competitive position in the marketplace estimated at €131 million. An alternative assessment of the overall damage made by Alitalia stands at €395 million of which €334 million of higher purchase costs for jet fuel and €61 million of lower profitability due to the reduced competitive position on the marketplace. The proceeding of first instance is at a preliminary stage, as a number of pre-trial issues determined a substantial stalemate situation.

3. Antitrust, EU Proceedings, Actions of the Authority for Electricity and Gas and of other Regulatory Authorities

  1. Inquiries in relation to alleged anticompetitive agreements in the area of elastomers – Prosecuting Body: European Commission. On November 29, 2006, the European Commission ascertaining anticompetitive agreements in the field of BR and ESBR elastomers fined Eni and its subsidiary Versalis SpA (former Polimeri Europa SpA) for an amount of €272.25 million. Eni and its subsidiary filed claims against this decision before the European Court of First Instance in February 2007. On July 13, 2011, the First Instance Court filed the decision to reduce the above mentioned fine to the amount of €181.5 million. In particular the Court annulled the increase of the fine related to the aggravating circumstance of recidivism. The companies involved in the decision and the European Commission filed a claim before the European Court of Justice. In addition the European Commission communicated to the decision to start an inquiry for the determination of a new sanction. The Company filed an appeal against this decision. On March 1, 2013, the Commission communicated to Eni and Versalis the commencement of a new proceeding for a new evaluation of the existence of the requirement for the application of an increased fine based on the aggravating circumstance of recidivism. In August 2007, with respect to the above mentioned decision of the European Commission, Eni submitted a request for a negative ascertainment with the Court of Milan aimed at proving the non-existence of alleged damages suffered by tire BR/SBR manufacturers. This judgement is pending. Then, subsidiaries of Dow Chemical summoned Eni and Versalis in order to be indemnified and held harmless as part of a proceeding commenced before the Commercial Court of London where tyre producers have been claiming compensation for the damages which were allegedly caused by the companies which have been part of the alleged trust on BR elastomers, among which the same Dow Chemical. Eni, Versalis and Dow Chemical have agreed to suspend the judgement also because Eni and Versalis have appealed the jurisdiction of the British Court. In December 2012, the First Instance Court of the European Union reduced to €106 million the fine imposed to Eni and its subsidiary Polimeri Europa from the original amount of €132.16 million sanctioned on December 5, 2007, relating to alleged anti competitive practices in the in CR elastomers sector, with other chemical companies, in violation of article 81 of EC Treaty and of article 53 of SEE agreement. In March 2013, Eni and Versalis have appealed against this decision before the EU Court of Justice in order to obtain the complete annulment of the economic sanction. Also the European Commission has appealed against the decision. Pending the decision, Eni accrued a provision with respect to this proceeding.

  2. Preliminary investigation of the Italian Authority for Electricity and Gas about the invoicing to retail clients of gas and electricity. With a resolution on October 31, 2013, the Italian AEEG resolved to commence a preliminary investigation to ascertain whether Eni violated certain administrative provisions that regulate the periodical invoicing in the retail selling of gas and electricity. The investigation also includes alleged delays in the invoice of certain documentation which is required in case of change of supplier. Upon the finalization of the investigation, the AEEG may impose an administrative sanction including a possible fine in accordance to Law 481/95 currently not estimable.

4. Court inquiries

  1. EniPower SpA. In June 2004, the Milan Public Prosecutor commenced inquiries into contracts awarded by Eni’s subsidiary EniPower and on supplies from other companies to EniPower. These inquiries were widely covered by the media. It emerged that illicit payments were made by EniPower suppliers to a manager of EniPower who was immediately dismissed. The Court presented EniPower (commissioning entity) and Snamprogetti (now Saipem SpA) (contractor of engineering and procurement services) with notices of process in accordance with existing laws regulating the administrative responsibility of companies (Legislative Decree No. 231/2001). In accordance with its transparency and integrity guidelines, Eni took the necessary steps in acting as plaintiff in the expected legal action in order to recover any damage that could have been caused to Eni by the illicit behavior of its suppliers and of their and Eni employees. In the meantime, preliminary investigations have found that both EniPower and Snamprogetti are not to be considered defendants in accordance with existing laws regulating the administrative responsibility of companies (Legislative Decree No. 231/2001). In August 2007, Eni was notified that the Public Prosecutor requested the dismissal of EniPower SpA and Snamprogetti SpA, while the proceeding continues against former employees of these companies and employees and managers of the suppliers under the provisions of Legislative Decree No. 231/2001. Eni SpA, EniPower and Snamprogetti presented themselves as plaintiffs in the preliminary hearing. In the preliminary hearing related to the main proceeding on April 27, 2009, the Judge for the Preliminary Hearings requested all the parties that have not requested the plea-bargain to stand in trial, excluding certain defendants as a result of the statute of limitations. During the hearing on March 2, 2010, the Court confirmed the admission as plaintiffs of Eni SpA, EniPower SpA and Saipem SpA against the inquired parts under the provisions of Legislative Decree No. 231/2001. Further employees of the companies involved were identified as defendants to account for their civil responsibility. After the filing of the pleadings occurred in the hearing of July 12, 2011, the proceeding was postponed to September 20, 2011. In that date the Court of Milan concluded that nine persons were guilty for the above mentioned crimes. In addition they were sentenced jointly and severally to the payment of all damages to be assessed through a dedicated proceeding and to the reimbursement of the proceeding expenses incurred by the plaintiffs. The Court also resolved to dismiss all the criminal indictments for 7 employees, representing some companies involved as a result of the statute of limitations while the trial ended with an acquittal of 15 individuals. In relation to the companies involved in the proceeding, the Court found that 7 companies are liable based on the provisions of Legislative Decree No. 231/2001, imposing a fine and the disgorgement of profit. Eni SpA and its subsidiaries, EniPower and Saipem which took over Snamprogetti, acted as plaintiffs in the proceeding also against the mentioned companies. The Court rejected the position as plaintiffs of the Eni Group companies, reversing a prior decision made by the Court. This decision may have been made probably on the basis of a pronouncement made by a Supreme Court which stated the illegitimacy of the constitution as plaintiffs made against any legal entity which is indicted under the provisions of Legislative Decree No. 231/2001. The Court filed the ground of the judgement in December 19, 2011.

    The condemned parties filed an appeal against the above mentioned decision. The appeal court issued a ruling which substantially confirmed

    the first-degree judgement except for the fact that it ascertained the statute of limitation with regard to certain defendants.

  2. TSKJ Consortium Investigations by US, Italian, and other Authorities. Snamprogetti Netherlands BV has a 25% participation in the TSKJ Consortium companies. The remaining participations are held in equal shares of 25% by KBR, Technip, and JGC. Beginning in 1994 the TSKJ Consortium was involved in the construction of natural gas liquefaction facilities at Bonny Island in Nigeria. Snamprogetti SpA, the holding company of Snamprogetti Netherlands BV, was a wholly owned subsidiary of Eni until February 2006, when an agreement was entered into for the sale of Snamprogetti to Saipem SpA and Snamprogetti was merged into Saipem as of October 1, 2008. Eni holds a 43% participation in Saipem. In connection with the sale of Snamprogetti to Saipem, Eni agreed to indemnify Saipem for a variety of matters, including potential losses and charges resulting from the investigations into the TSKJ matter referred to below, even in relation to Snamprogetti subsidiaries. In recent years the proceeding was settled with the US Authorities and certain Nigerian Authorities, which had been investing into the matter.

    The proceedings in the US: following an investigation that lasted several years, in 2010 the Department of Justice and the SEC entered into settlements with each of the TSKJ consortium members. In particular, in July 2010, Snamprogetti Netherlands BV entered into a deferred prosecution agreement with the DoJ, consented to the filing of criminal information, and agreed to pay a fine of $240 million. In addition Snamprogetti Netherlands BV and Eni reached an agreement with the SEC to resolve the investigation and jointly agreed to pay disgorgement to the SEC of $125 million. All amounts due to the US Authorities were paid by Eni in accordance with the indemnity granted by Eni in connection with its sale of Snamprogetti to Saipem. Following the two-year period set out in the deferred prosecution agreement, in September 2012 the DoJ dismissed the criminal information filed against Snamprogetti Netherlands BV, thereby dismissing the criminal proceeding against Snamprogetti Netherlands BV.

    The proceedings in Italy: the events under investigation covered the period since 1994 and also concerned the period of time subsequent to the June 8, 2001, enactment of Italian Legislative Decree No. 231 concerning the liability of legal entities. The proceeding set by the Public Prosecutor of Milan investigated Eni SpA and Saipem SpA for liability of legal entities arising from offences involving alleged international corruption charged to former managers of Snamprogetti SpA. The Public Prosecutor of Milan requested Eni SpA and Saipem SpA to be debarred from activities involving – directly or indirectly – any agreement with the Nigerian National Petroleum Corporation and its subsidiaries. In particular, the Public Prosecutor claimed the inadequacy and violation of the organizational, management and control model adopted to prevent those offences charged to people subject to direction and supervision. Subsequently, the Public Prosecutor of Milan, with respect to the guarantee payment amounting to €24,530,580 even in the interest of Saipem SpA, renounced to contest the decision of rejection of precautionary measures of disqualification for Eni SpA and Saipem SpA. The charged crimes involved alleged corruptive events that have occurred in Nigeria after July 31, 2004. It is also stated the aggravating circumstance that Snamprogetti SpA reported a relevant profit (estimated at approximately $65 million). The Public Prosecutor requested five former employees of Snamprogetti SpA (now Saipem) and Saipem SpA (as legal entity incorporating Snamprogetti) to stand trial. In the course of the proceeding, the Court dismissed the case with respect to the position of the individuals who were acting as plaintiffs for the expiration of the statute of limitations while the proceeding continued for Saipem SpA. Afterwards, the Court condemned Saipem SpA to pay a fine amounting to €600,000 and the disgorgement of the guarantee payment of €24,530,580, made by Snamprogetti Netherlands BV. Saipem filed an appeal against the sentence issued by the First Instance Court. At the moment, the date of the hearing has not been scheduled.

  3. Gas metering. With the proceeding No. 11183/06 the Public Prosecutor at the Court of Milan accused Eni, certain top managers of Eni and of the Group companies of alleged breaches of the Italian Criminal Law, starting from 2003, regarding the use of instruments for measuring gas, in relation to the payments of excise duties and the billing of clients as well as relations with the Supervisory Authorities. The allegation regards, inter alia, the offense contemplated by Legislative Decree of June 8, 2001, No. 231, which establishes the liability of the legal entity for crimes committed by its employee in the interests of such legal entity, or to its advantage. Accordingly, notice of the commencement of investigations was served upon Eni Group companies (Eni, Snam Rete Gas and Italgas) as well as third party companies. During the years, the investigations of the Public Prosecutor led to two distinctive proceedings known as “the Croatian Gas” and “Excise Duties”. The first proceeding was dismissed against all defendants by the Judge of the Preliminary Hearing on January 24, 2012. The Supreme Degree Court confirmed the Judge decision against the recourse presented by the public prosecutors, who nonetheless challenged the Judge decision only in relation with a few defendants. Also the proceeding about excise duties resulted in a favourable outcome to all defendants – who were employees and former employees of Eni’s Gas & Power Division – because the Judge ascertained that the investigated facts did not enter into the specifics of the alleged crimes. Again in 2013, the Supreme Degree Court confirmed the Judge decision against the recourse presented by the public prosecutors.

  4. Algeria – Corruption investigation. Authorities in Italy and in other Countries are investigating allegations of corrupt payments in connection with the award of certain contracts to Saipem. On February 4, 2011, Eni received from the Public Prosecutor of Milan an information request pursuant to Article 248 of the Italian Code of Criminal Procedure. The request related to allegations of international corruption and pertained to certain activities performed by Saipem Group companies in Algeria (in particular the contract between Saipem and Sonatrach relating to the construction of the GK3 gas pipeline and the contract between Galsi, Saipem and Technip relating to the engineering of the ground section of a gas pipeline). For that reason, the notification was forwarded by Eni to to Saipem. The crime of international corruption is among the offenses contemplated by Legislative Decree of June 8, 2001, No. 231, relating to corporate responsibility for crimes committed by employees which provides fines and interdictions to the company and the disgorgement of profit. Saipem promptly began to collect documentation in response to the requests of the Public Prosecutor. The documents were produced on February 16, 2011. Eni also filed documentation relating to the MLE project (in which the Eni’s Exploration & Production Division participates) even if not required, with respect to which investigations in Algeria are ongoing. On November 22, 2012, the Public Prosecutor of Milan served Saipem a notice stating that it had commenced an investigation for alleged liability of the Company for international corruption in accordance to Article 25, second and third paragraph of Legislative Decree No. 231/2001. Furthermore the prosecutor requested the production of certain documents relating to certain activities in Algeria. Subsequently, on November 30, 2012, Saipem was served a notice of seizure, then, on December 18, 2012, a request for documentation and finally, on January 16, 2013, a search warrant was issued, in order to acquire further documentation in particular relating to certain intermediary contracts and sub-contracts entered into by Saipem in connection with its Algerian business. The investigation relates to alleged corruption which, according to the Public Prosecutor, had occurred with regard to certain contracts awarded to Saipem in Algeria up until March 2010. The former CEO of Saipem, who was resigned from the office at the end of 2012, and the former COO of the business unit Engineering & Construction of Saipem, who was fired at the beginning of 2013, as well as other Saipem employees and former employees are under investigation. On February 7, 2013, on mandate from the Public Prosecutor of Milan, the Italian financial police visited Eni’s headquarters in Rome and San Donato Milanese and executed searches and seized documents relating to Saipem’s activity in Algeria.

    On the same occasion, Eni was served a notice that an investigation had commenced in accordance with Article 25, third and fourth paragraph of Legislative Decree No. 231/2001 with respect to Eni, Eni’s CEO, Eni’s former CFO, and another senior manager. Eni’s former CFO had previously served as Saipem’s CFO including during the period in which alleged corruption took place and before being appointed as CFO of Eni in 2008. He departed from Eni in connection with the bribery investigation. The proceeding was unified with the Iraq – Kazakhstan proceeding, concerning a different line of investigation, as it related to the activities carried out by Eni in Iraq and Kazakhstan. More information is provided in the specific section of this report. Saipem, which is fully cooperating with the judicial Authority since the beginning of the investigation, has also promptly undertaken management and administrative changes. Saipem has commenced an internal investigation in relation to the contracts in question with the support of external advisors; such internal investigation is conducted in agreement with the statutory bodies deputed to the Company’s control and the Italian Public Prosecutor has been informed of this internal investigation. In addition, in the course of 2013, Saipem has completed a review aimed at verifying the correct application of internal procedures and controls relating to anti-corruption and prevention of illicit activities, with the assistance of external consultants. Saipem provided Eni the findings of its internal review; Eni is still evaluating those findings. Moreover, Saipem’s Board resolved to initiate legal action to protect the interests of the Company against certain former employees and suppliers, reserving any further action if additional factors emerge. In August 2013, in relation to the criminal proceeding the press reported that the former Chief Operating Officer of the Business Unit Engineering & Construction of Saipem, who had been fired by the company, was subject to a precautionary detention measure in prison. This measure, as reported by the press, was subsequently canceled in December 2013 by granting house arrest. Finally, as requested by the US Department of Justice (DoJ), in the course of 2013, Saipem entered into a tolling agreement with the DoJ to extend the statute of limitations applicable to possible violations of the federal laws of the USA in relation to certain past activities conducted by Saipem and its subsidiaries.

    The tolling agreement does not constitute an admission on part of Saipem of any wrongdoing or a concession of the jurisdiction of the USA to bring a proceeding. Saipem intends to fully cooperate also as part of any possible investigation made by US Authorities. Furthermore, Eni, albeit denying any involvement in the matter, has commenced an internal investigation with the assistance of external consultants, in addition to the review activities performed by its audit and internal control departments and a dedicated team to the Algerian matters. To date, excepting further investigation if necessary, the following preliminary results have been reached: (i) the review of the documents seized by the Milan prosecutors and the examination of internal records held by Eni’s global procurement department have not found any evidence that Eni entered into intermediary or any other contractual arrangements with the third parties involved in the prosecutors’ investigation; the brokerage contracts, that have identified, were signed by Saipem or its subsidiaries or predecessor companies; (ii) the internal review made on a voluntary basis of the MLE project, the only project that Eni understands to be under the prosecutors’ investigation where the client is an Eni group company. That review has not found evidence that any Eni employee engaged in wrongdoing in connection with the award to Saipem of two main contracts to execute the project (EPC and Drilling). The findings of Eni’s internal review have been provided to the judicial Authority in order to reaffirm Eni’s willingness to fully cooperate. Furthermore, with the assistance of external consultants, Eni has been reviewing the extent of its operating control over Saipem with regard to both legal and accounting and administrative issues. The findings of the review performed have confirmed the autonomy of Saipem from the parent company. Finally, Eni has contacted the US Authorities – the DoJ and the US SEC – in order to voluntary inform them about this matter, considering the developments in the Italian prosecutors’ investigations since the end of 2012. Following this informal contact between Eni and the US Authorities, both the US SEC and the DoJ have started their own investigations about this matter. Eni has furnished various information and documents, including the findings of its internal reviews, in response to formal and informal requests. Investigations are also ongoing in Algeria where the bank accounts of a Saipem’s subsidiary, Saipem Contracting Algérie SpA, have been blocked by the Algerian Authorities with a balance equivalent to about €80 million at current exchange rates. Those bank accounts related to two ongoing projects in Algeria. In 2012, a notice of investigation was served to Saipem Contracting Algérie SpA. The company is alleged to have taken advantage of the Authority or influence of representatives of a government owned industrial and trading company in order to inflate prices in relation to contracts awarded by said company. In January 2013, the Judicial Authority in Algeria ordered Saipem’s Algerian subsidiary to stand trial and reaffirmed the blockage of the above mentioned bank accounts. Saipem Contracting Algérie SpA has lodged an appeal against this decision before the Supreme Court. Furthermore, also the parent company Saipem is being investigated by the Judicial Authority in Algeria for alleged corrupt payments. The various authorities are ongoing and it is not possible to predict their outcome. They could result in legal liability on the part of individuals or entities found in violation of the FCPA, Italian and other anti-corruption laws.

  5. Iraq – Kazakhstan. A criminal proceeding is pending before the Public Prosecutor of Milan in relation to alleged crimes of international corruption involving Eni’s activities in Kazakhstan regarding the management of the Karachaganak plant and the Kashagan project, as well as handling of assignment procedures of work contracts by Agip KCO. The crime of “international corruption” is sanctioned, in accordance to the Italian criminal code, by Legislative Decree June 8, 2001 No. 231 which holds legal entities liable for the crimes committed by their employees on their behalf. The Company has filed the documents collected and is fully collaborating with the Public Prosecutor. A number of managers and a former manager are involved in the investigation. The above mentioned proceeding has been reunified with another (the so-called “Iraq proceeding”) regarding a parallel proceeding related to Eni’s activities in Iraq, disclosed in the following paragraphs. On June 21, 2011, Eni Zubair SpA and Saipem SpA in Fano (Italy) were notified that a search warrant had been issued to search the offices and homes of certain employees of the Group and of certain third parties. In particular the homes and offices of an employee of Eni Zubair and a manager of Saipem were searched by the Authorities. The accusation is of criminal conspiracy and corruption in relation with the activity of Eni Zubair in Iraq and of Saipem in the “Jurassic” project in Kuwait. The Public Prosecutor of Milan has charged Eni Zubair, Eni and Saipem with the accusations as a result of the alleged illicit actions of their employees. If the charges are valid, Eni considers those employees to have breached the Company’s Code of Ethics. The Eni Zubair employee resigned and the Company, accepting the resignation, reserved the right to take action against the individual to defend its interests and subsequently commenced a legal action against the other persons mentioned in the seizure act. Notwithstanding that the Eni Group companies appear to be offended parties in respect of the illicit conduct under investigation associated with these accusations, Eni SpA and Saipem SpA also received, at the same time the search warrant was issued, a notification pursuant to the Legislative Decree No. 231/2001. Eni SpA was notified by the Public Prosecutor of a request of extension of the preliminary investigations that has led up to the involvement of another employee as well as other suppliers in the proceeding. Eni performed a review of the whole matter also with the support of an external consulting firm which issued its final appraisal report on July 25, 2012. According to the opinion of its legal team, the Company’s watch structure and Internal control committee, Saipem too commenced through its Internal Audit department an internal review about the project with the support of an external consultant. The Public Prosecutor of Milan requested Eni SpA to be debarred for one year and six months from performing any industrial activities involving the production sharing contract of 1997 with the Republic of Kazakhstan and in the subsequent administrative or commercial arrangements, or the prosecution of the mentioned activities under the supervision of a commissioner pursuant to article 15 of the Legislative Decree No. 231 of 2001. In the subsequent hearings, Eni filed defensive memorandum; also the Public Prosecutor filed further documentation supporting the request of precautionary measures. On July 16, 2013, the Judge for Preliminary Investigation rejected the request for precautionary measures requested by the Public Prosecutor of Milan, because considered groundless. The Public Prosecutor promptly appealed the decision before a higher-degree court. After the appeal hearing, on October 21, 2013 such court rejected the appeal filed by the Public Prosecutor. The Re-examination Court rejected the appeal with judgment upon the merits due to the lack of serious evidence against Eni, accepting the defence arguments for which Eni suffered severe damages as a consequence of poor performances of some suppliers involved in the Kashagan project. In addition, the Court declared the lack of precautionary requirements considering the reorganization of the activities in Kazakhstan and taking into account of the initiatives of internal audit and control promptly adopted by Eni. The Public Prosecutor’s office did not appeal against the sentence of the Re-examination Court. Also based on this decision, on March 13, 2014, the Eni legal team requested to the Public Prosecutor to dismiss the proceeding.

5. Tax Proceedings

Italy

  1. Eni SpA – Dispute for the omitted payment of a municipal tax related to oil platforms located in territorial waters in the Adriatic Sea. With a formal assessment presented in December 1999, the Municipality of Pineto (Teramo) claimed Eni SpA omitted payment of a municipal tax on real estate for the period from 1993 to 1998 on four oil platforms located in the Adriatic Sea which constitute municipal waters. Eni was requested to pay a total of approximately €17 million including interest and a fine. Eni filed a counterclaim stating that the sea where the platforms are located is not part of the municipal territory and the tax application as requested by the Municipality lacked objective fundamentals. The claim has been accepted in the first two degrees of judgment at the Provincial and Regional Tax Commissions. However, the supreme degree Court overturned both judgments, declaring that a Municipality can consider requesting a tax on real estate in the sea facing its territory and with the decision of February 2005 sent the proceeding to another section of the Regional Tax Commission in order to rule on the matters of the proceeding. This commission requested an independent consultant to assess the tax and technical aspects of the matter. The independent consultant confirmed that Eni’s offshore installations lack any ground to be subject to the municipal tax that was claimed by the local Municipality. Those findings were accepted by the Regional Tax Commission with a ruling made on January 19, 2009. On January 25, 2011, the Municipality notified Eni of an appeal to the Supreme Degree Court for the cancellation of the above mentioned ruling. Also on December 28, 2005, the Municipality of Pineto presented similar claims relating to the same Eni platforms for the years 1999 to 2004. The total amount requested was €25 million including interest and penalties. Eni filed a counterclaim which was accepted by the First Degree Judge with a decision of December 4, 2007. Also a second degree court ruled in favour of Eni’s recourses with a sentence filed on June 2012. Terms are pending to file a counterclaim before a third degree court. Similar formal assessments related to Eni oil and gas offshore platforms were presented by the Municipalities of Falconara Marittima, Tortoreto, Pedaso, and also from 2009 the Gela Municipality. The total amounts of those claims were approximately €7.5 million. The Company filed appeal against all those claims. A tax commission in Sicily ruled in favour of Eni accepting the recourse against the tax claims presented by the municipality of Gela.

Outside Italy

  1. Eni Angola Production BV. In 2009 the Ministry of the Finance of Angola, following a fiscal audit, filed a notice of tax assessment for fiscal years 2002 to 2007 in which it claimed the improper deductibility of amortization charges recognized on assets in progress related to the payment of the Petroleum Income Tax that was made by Eni Angola Production BV as co-operator of the Cabinda concession. The Company filed an appeal against this decision. The judgment is still pending before the Supreme Court. Eni accrued a provision with respect to this proceeding.

  2. Eni’s subsidiary in Indonesia. A tax proceeding is pending against Eni’s subsidiary Lasmo Sanga Sanga Ltd as the Tax Administration of Indonesia has questioned the application of a tax rate of 10% on the profit earned by the local branch of Eni’s subsidiary for fiscal years 2002 through 2009. Eni’s subsidiary, which is resident in the UK for tax purposes, believes that the 10% tax rate is warranted by the current treaty for the avoidance of double taxation. On the contrary, the Tax Administration of Indonesia has claimed the application of the local tax rate of 20%.

    The greater taxes due in accordance to the latter rate have been disbursed amounting to $134 million including interest expense. Eni’s subsidiary has filed an appeal claiming the opening of an amicable procedure to settle the matter and avoid bearing a tax regime not in compliance with the UK/Indonesia treaty. Eni accrued a provision with respect to this proceeding.

6. Settled legal proceedings

  1. Investigation of the quality of groundwater in the area of the Refinery of Gela. This criminal proceeding held by the Public Prosecutor of Gela relating to alleged pollution of ground at the Eni Gela Refinery was dismissed because the statute of limitations expired.

  2. Alleged negligent fire (Priolo). Due to the immateriality of the proceeding, no more information will be reported about a pending investigation of the Public Prosecutor of Siracusa relating to certain Eni managers who were in charge of conducting operations at the Refinery of Priolo aimed at ascertaining whether Eni they acted with negligence in connection with a fire that occurred at the Priolo plants on April 30 and May 1-2, 2006.

  3. Groundwater at the Priolo site – Prosecuting body: Public Prosecutor of Siracusa. The Public Prosecutor of Siracusa who has started an investigation in order to ascertain the level of contamination of the groundwater at the Priolo site requested to dismiss the case.

  4. Syndial SpA (former EniChem SpA) – Claim of environmental damages, allegedly caused by industrial activities in the area of Crotone – Prosecuting Bodies: the Council of Ministers, the Ministry for the Environment, the Delegated Commissioner for Environmental Emergency in the Calabria Region and the Calabria Region. The Council of Ministers, the Ministry for the Environment, the Delegated Commissioner for Environmental Emergency in the Calabria Region and the Calabria Region summoned Syndial before the Civil Court of Milan to obtain a sentence condemning the Eni subsidiary to compensate the environmental damage and clean-up and remediation costs caused by the operations of Pertusola Sud SpA (merged in EniChem, now Syndial) at the Crotone site. The original compensation claimed for environmental remediation and clean-up amounted to €2,720 million which comprised both the Calabria Region claims and the Ministry for the Environment claims. In order to settle the whole matter, in 2008 Syndial decided to take over the remediation activities in the area and on December 5, 2008 filed a comprehensive clean-up project. This project, which was approved in almost its entirety by the Ministry for the Environment and the Calabria Region, has been considered substantially adequate also by the Court. On February 24, 2012, the Court sentenced Syndial to correctly execute the environmental clean-up of the site in accordance with the approved remediation plan and to pay to the Presidency of the Council of Ministers and the Ministry for Environment the sum of €56.2 million plus interest charges accrued from the plaintiffs’ claims. The sentence of the Court has now become final.

  5. Saipem SpA – CEPAV Uno. Saipem holds an interest in the CEPAV Uno consortium (50.36%) which in 1991 signed a contract with TAV SpA (now RFI – Rete Ferroviaria Italiana SpA) for the construction of a fast-track railway infrastructure for high speed/high capacity trains from Milan to Bologna. An arbitration proceeding has arisen to define certain amounts claimed by the Consortium against the buyer for alleged changes in the scope of work, as the counterparties failed to reach an amicable settlement of the issues. The Arbitration Committee resolved a partial award to the consortium amounting to €54.253 million that was disbursed by RFI on February 7, 2013. Then, the consortium filed three further claims amounting to €2,108 million to take into account alleged damages, higher costs incurred for changes in the scope of work and other factors in addition to interest accrued and revaluation. In December 2013, the Consortium and RFI entered into a global transaction whereby RFI paid €200 million to compensate the Consortium for all pending claims, including the partial award of the arbitration experts. RFI will give the Consortium the agreed 80% of the performance bids and the relevant advances.

  6. Inquiry in relation to gas transportation. The inquiry held by the Italian Antitrust Authority about alleged anti competitive behaviour charged to Eni in connection with the refusal to dispose of secondary transport capacity on the Transitgas and TAG pipelines to third parties was dismissed following acceptance by the Authority of the commitments presented by Eni.

  7. Trading. In the investigation regarding two former Eni managers who were allegedly bribed by third parties to facilitate the conclusion of transactions with oil trading companies, Eni was acting as plaintiff in this proceeding and summoned the two people to be compensated for the economic damages suffered through the abuse of working relations and activities. The proceeding closed due to the statute of limitations with respect to the above mentioned managers.

  8. Libya. On June 10, 2011, Eni received by the US SEC a formal judicial request of collection and presentation of documents (subpoena) related to Eni’s activity in Libya from 2008 until now in relation to an ongoing investigation without further clarifications or specific alleged violations in connection to “certain illicit payments to Libyan officials” possibly violating the US Foreign Corruption Practice Act. Following a number of discussions with the US SEC and the provision of information and documentations, on April 29, 2013, the US SEC communicated to Eni the closing of the investigations without further claims or other observations.

Assets under concession arrangements

Eni operates under concession arrangements mainly in the Exploration & Production segment and the Refining & Marketing segment. In the Exploration & Production segment contractual clauses governing mineral concessions, licenses and exploration permits regulate the access of Eni to hydrocarbon reserves. Such clauses can differ in each Country. In particular, mineral concessions, licenses and permits are granted by the legal owners and, generally, entered into with government entities, State oil companies and, in some legal contexts, private owners. As a compensation for mineral concessions, Eni pays royalties and taxes in accordance with local tax legislation. Eni sustains all the operational risks and costs related to the exploration and development activities and it is entitled to the productions realized. In Production Sharing Agreement and in buyback contracts, realized productions are defined on the basis of contractual agreements drawn up with State oil companies which hold the concessions. Such contractual agreements regulate the recovery of costs incurred for the exploration, development and operating activities (cost oil) and give entitlement to the own portion of the realized productions (profit oil). In the Refining & Marketing segment several service stations and other auxiliary assets of the distribution service are located in the motorway areas and they are granted by the motorway concession operators following a public tender for the sub-concession of the supplying of oil products distribution service and other auxiliary services. Such assets are amortized over the length of the concession (generally, 5 years for Italy). In exchange of the granting of the services described above, Eni provides to the motorway companies fixed and variable royalties on the basis of quantities sold. At the end of the concession period, all non-removable assets are transferred to the grantor of the concession. Assets under concessions relating to natural gas storage in Italy and to the gas distribution of the Gas & Power segment pertained to Snam Group that was deconsolidated following the sale of control.

Environmental regulations

Risks associated with the footprint of Eni’s activities on the environment, health and safety are described in “Financial Review”, paragraph “Risk factors and uncertainties”. In the future, Eni will sustain significant expenses in relation to compliance with environmental, health and safety laws and regulations and for reclaiming, safety and remediation works of areas previously used for industrial production and dismantled sites. In particular, regarding the environmental risk, management does not currently expect any material adverse effect upon Eni’s consolidated financial statements, taking account of ongoing remedial actions, existing insurance policies and the environmental risk provision accrued in the consolidated financial statements. However, management believes that it is possible that Eni may incur material losses and liabilities in future years in connection with environmental matters due to: (i) the possibility of as yet unknown contamination; (ii) the results of the ongoing surveys and the other possible effects of statements required by Legislative Decree No. 152/2006 of the Ministry for the Environment; (iii) new developments in environmental regulation; (iv) the effect of possible technological changes relating to future remediation; and (v) the possibility of litigation and the difficulty of determining Eni’s liability, if any, as against other potentially responsible parties with respect to such litigation and the possible insurance recoveries.

Emission trading

The third phase of the European Union Emissions Trading Scheme (EU-ETS) came in force since January 1, 2013. Phase three sees a turn in the main method of assignment of the permits that change from allocating for free on the base of historical emissions to allocating through auctioning. In particular, for the period 2013-2020, the free allocation of permits is done using European benchmarks specific to each industrial segment, except for the thermoelectric sector which is not eligible for free allocations. For this reason, starting from 2013, Eni benefits from a lower allocation of emission permits compared to the emissions provided for plants subject to emissions trading. This situation implies for Eni a progressive use of the permits accumulated in the period 2008-2012 and, subsequently, the supplying of the amounts required by the compliance through the marketplace. As of December 31, 2013, the final quotas freely assigned to Eni’s plants for the period 2013-2020 are still under approval by each state of the European Union. In 2013, the emissions of carbon dioxide from Eni’s plants were higher than the permits assigned. Against emissions of carbon dioxide amounting to approximately 20.42 millions tonnes were assigned to Eni emission permits for a total amount of 9.24 million tonnes, determining a deficit of 11.8 million tonnes. This deficit was partially offset by using permits accumulated in the period 2008-2012 (7.14 million tons), while the remaining emissions permits were acquired through the marketplace (4.04 million tonnes).